access for all

an Exeter community partnership

Second Phase

The
St Stephen's

Project

 
 

Brochure

Latest News

Galleries

Make it Happen

Project Reports

 

Funding Progress to May 2010

The £962,840 raised to date provides 62% of the total sum required to complete both Phase 1 and Phase 2 of the St Stephen's Project.

>>> Full Funding Report

Activities in March and April 2010

During March, we were informed that the Diocesan Advisory Committee agreed to issue a certificate of approval to proceed with the second phase of the Project. There are a number of proviso's included with this certificate mainly linked to the need to produced further detail relating to the proposed lighting, the art work in the south-facing windows and the window/door conversion. These are currently being worked on. With the DAC certificate to hand a petition for a full faculty to proceed with the work required has been lodged with the Diocesan Registrar. To go with this, a public consultation period commenced on 17th April and is to be concluded on 15th May. This consultation requires the display of the proposed plans and other documents in St Stephen's with an invitation to consult them on notice boards both inside and outside the church. This procedure is required owing to the antiquity of the building and in recognition of the right of the public to be consulted.

>>> More activities
>>> Updated Financial Statement (Report 31)

Annual Report 2009

In the first of six progress reports issued in 2009 it was stated that January 2009 marked the start of Phase 2 of the St Stephen's Project. During this concluding phase the lower-level external repairs and the full re-ordering of the interior of St Stephen's are planned to take place. While the development and administration of this phase of the Project is seen as a whole, the building works are planned to proceed in a series of sections. But before any building work can be undertaken it is necessary to prepare the detailed design of the phase as a whole in order to proceed with the proposed works. With this in mind, detailed discussions began in January and continued in one form or another throughout 2009. At the same time and after the successful completion of Phase 1 at a cost of over £450,000, seeking funds to complete Phase 2 was commenced with enthusiasm >>> read more

Income and Expenditure Account for 2009 >>> read more

Activities in January and February 2010

As 2010 proceeds, good news abounds. Our major sponsor for Phase 2 of the Project, Viridor Credits, is having a re-think concerning the restriction of using the grant they have promised for development costs. A meeting took place in January during which the difficulty of reconciling cash-flow needs in paying our professional advisers and meeting the advance contribution required to release the promised grant while at the same time attempting to raise funds for the next tranche of development costs was fully discussed. Part of the problem is due to the (necessary) requirement that no contracts for work are initiated unless the funds to meet the costs of such work are available. This combined with a restriction for paying development costs created a very difficult situation for our fundraising effort. As a result of this meeting, strong efforts were made to find sufficient funds to meet the grant release contribution of £40,936; this was forwarded to Viridor Credits in early February followed shortly by a claim of £54,300 to cover payments already made. This allows us to return the short-term loans we were obliged to seek.

>>> More activities
>>> Updated Financial Statement (Report 30)

Activities in November and December 2009

This period started with a flurry owing to the need to get all reports ready for the submission to the Diocese for permission to proceed by November 20th. There was uncertainty about the siting of the gas boiler room for the central heating system. St Stephen's has no out-buildings or places where equipment can be stored away from the main body of the church. It was initially suggested that the boilers should be placed in a corner of the body of the church enclosed by a screen but this was abandoned owing to the close proximity to the dais. There was concern about possible noise during performances or church services. The only possible alternative place for the boiler room was in the intermediate room half way up the tower and above the proposed meeting rooms. The logistics in arranging this site for a boiler room are problematic and potentially expensive but it has to be. This meant re-drawing the plans involving considerable work by the professional team within a tight time frame. The boilers are necessary to provide the under-floor heating system as well as a hot water supply to the new servery.

>>> More activities
>>> Updated Financial Statement (Report 29)

Activities in September and October 2009

This has been a heavy period for the professional consultants employed on the Project. Once it became apparent that the cost of professional fees could be met and contracts signed, the signal was given to prepare the detailed plans and reports necessary to gain official permission for the work to go ahead.

>>> More activities
>>> Updated Financial Statement (Report 28)

Activities in July and August 2009

This period has introduced the ups and downs of fundraising in a big way. The agreement letter with Viridor Credits, who are responsible for the administration of the £400,000 Landfill Community Fund grant previously negotiated, has been signed at our end at last. The delay and uncertainty arose as the previously accepted cost estimates based on the building works needed to be translated into the actual timing of payments - especially where the cost of the detailed planning preparation required has to be met in advance of the building work. Permission to proceed with this phase of the Project has been agreed 'in principle' but detailed drawings etc. are required before building work can actually start.

>>> More activities
>>> Updated Financial Statement (Report 27)

Activities in May and June 2009

The financial support being received and promised has meant that we can begin the detailed development work for this phase of the Project. Contracts have been signed with our architect, with new consulting engineers, with our surveyor and with our health and safety consultant; others will, no doubt, follow. The first task is to prepare for and submit detailed applications to gain the necessary permissions to proceed. Both the local Diocese and the Exeter City Council have agreed in principle to the work to come but now we need to produce the detail. There is much local interest in St Stephen's owing to its ancient origins and to its location in the very centre of Exeter.

>>> More activities
>>> Updated Financial Statement (Report 26)

Activities in March and April 2009

The annual assessment of the work undertaken on the St Stephen's roof and tower took place in early March and the architects were satisfied that Phase 1 of the Project can now be regarded as complete. The final (retained) payment to the contractors is being arranged. We can now fully concentrate on planning for Phase 2 of the Project

>>> More activities
>>> Updated Financial Statement (Report 25)

Annual Report 2008

The most important Project event during 2008 was the completion of Phase 1 - the repairs to the roof and tower - with St Stephen's declared safe and watertight with all bills paid. >>> read more

Income and Expenditure Account for 2008 >>> read more

St Stephen’s Project Accounts for the years 2003 to 2008 >>> read more

Activities in January and February 2009

January 2009 marked the beginning of the second phase of the St Stephen's Project. During this concluding phase the lower-level external repairs and the full re-ordering of the interior of St Stephen's are planned to take place. While the development and administration of this phase of the Project is seen as whole, the building works are planned to proceed in a series of seven stages. But before any building work can be undertaken it is necessary to prepare the detailed design of the phase as a whole to the level necessary to gain the permissions to proceed with the proposed works. With this in mind, detailed discussions took place during January and February with our commissioned architects and quantity surveyor. These resulted in agreement concerning the Phase 2 development costs and the proportions payable as the work proceeds. This is necessary in order to keep to the most important financial principle governing the funding of the Project; namely the need to have available the necessary funding (in the form of bank deposits or promises to pay from recognised grant-giving trusts) before any contract is signed. This requires the identification of the minimum sum required before any work can commence.

>>> More activities
>>> Updated Financial Statement (Report 24)

Activities in November and December 2008

A good deal of November was spent in visiting and re-visiting the printing firm responsible for producing the new project brochure and leaflet. These are now available and being sent out.

During this two-month period we have had good news from the Council for the Care of Churches who have offered us a grant of £4,000; a further £5,000 was received from the St Kerian;s Trust and £3,000 from the Foundation for Sport and the Arts. These grants have gone a long way in helping to pay for the organ repair and relocation.

>>> More activities
>>> Updated Financial Statement (Report 23)

 

If you have any questions or would like to help please contact the project team.

  This page was last updated on 10 June 2010.
If you would like to give us feedback on our website please e-mail us at webmaster@stephenproject.org.uk