|
News Archive |
|
|
August
Phase 1 is now completed. Faculty permission has been obtained
to move the in St Stephens organ to St Mary Arches in
November/December. A grant promise of £3,000 from the Foundation
for Sports and the Arts has been received to support this (total
cost £31,000); other fundraising is proceeding.
The Parish discussion on 6th July renewed emphasis on the access
for all theme for the re-ordered St Stephens in Phase 2 of the
Project. Publicity material is being prepared for the launch
after the summer.
Two generous personal donations each of £500 were received
towards the end of July to help introduce Phase 2. Please
support the Thursday lunchtime events in aid of the Project
during August. We still have a million pounds to raise! |
|
|
July
There will be an update for the Parish after the morning service
in St Mary Arches on 6th July.
Caroline’s voice workshop raised £128 (inc. Gift Aided
contributions) for the Project. She would like to say a big
“thank you” to those who attended, filled in the feedback forms
and gave so generously to the Project. To those who so
indicated, she'd be very happy to offer a follow-up 1-1 session
and, of course, at no charge!'
The public continue to give generous support to the Project.
Don’t forget the lunchtime free concerts each Thursday starting
July 31st. Thanks to all who help with these events... |
|
|
May/June
On We are now in a quieter period, as we prepare for a fresh
fundraising launch for the remaining work to be done both
outside and inside St Stephen’s. We are currently waiting for
information about the phasing of work and the funds needed, and
so the Parish discussion planned for May 4th is being postponed
to June or July.
The paperwork for seeking permission to move the organ to St
Mary Arches is now complete, and the final payments relating to
the Phase 1 repairs to the roof and tower are expected to take
place this month. |
|
|
April
On 14th March, St Stephen’s was formally handed
back to the Parish at the completion of the essential repairs to
the roof and tower. All are invited to the thanksgiving service
on Sunday 20th when the architect and others will be attending.
Before After Thanks to all those who contributed
to the successful completion of the external repairs. Funding is
currently being sought for the crypt assessment, moving the
organ to St Mary Arches and to meet the costs of preparing for
the next stage of the Project - the modernisation of the
interior. There is still a long way to go, but progress is being
made. |
|
|
March
The scaffolding has been removed! – a more complex task than
meets the eye.

Before
After
And back at ground level, the search has begun for the ancient crypt, last
officially visited in 1826. 20mm holes have been
drilled through the floor in various places in accordance with a
conjectural plan of where the crypt might be. A void has been
found beneath the floor and the archaeologist is preparing a
ground plan of where a larger hole might be made to permit
physical and lighting access.
Funding is currently being sought for the crypt
assessment, moving the organ to St Mary Arches and to meet the
costs of preparing for the next stage of the Project. There is
still a long way to go, but progress is being made. Thanks to
all who continue to support the Project, both practically and
prayerfully. |
|
|
February
he external rendering is currently being finished off;
scaffolding should be removed, starting towards the end of this
month. Completion is still expected in mid-March.
The Archaeology Unit has just produced a
detailed report about the crypt. Following a recent scan (very
difficult, owing to steel mesh laid in 1972), some drilling and
camera work is now proposed. There’s growing interest. Watch
this space! |
|
|
January
2008
The north aisle parapet has been rebuilt; the east gable damage
has been completely repaired, ‘tile stitching’ on the tower is
under way, the stair tower brickwork has been redone, the roof
structure’ felted’ and re-battened - and is now water-proof!!!!
The
top of the tower is finished, repairs to the body of the tower
are almost complete and nearly all of the new slates are in
place. We are still on target to complete works by the end of
February, with a cleaning of the Church during March and full
re-opening in April. The new timberwork and slates are almost
all in place. The timbers still show signs of incendiary bomb
burning from the 1942 blitz which left this building as the only
one standing in this part of Exeter. The tower needed more work
than expected. It is receiving essential strengthening to avoid
it falling into the High Street.
The parapet over the High Street could be moved
by hand after the cement rendering had been removed! We are
replacing this using as many of the ancient bricks as possible.
Other faults to the east end of the building have also been
found and put right. These works are expected to take until the
end of January to complete.
When the outside repairs are completed, we start
on the much bigger job of repairing inside St Stephen’s.
There is still a long way to go but with your
continued help we know we will get there.
|
|
|
December We’re well
into the Project now. The top of the tower is finished, repairs
to the body of the tower are 75% complete and 80% of the new
slates are in place. We are still on target to complete works by
the end of February, with a cleaning of the church during March
and full re-opening in April.
... View the latest photos
of the work There is to be a special service in St Stephen’s
commemorating the Project on Sunday 16th December at the usual
time of 11.00am. The service is to be led by the Dean, and the
design team have been invited, immediately afterwards, to
describe the work completed to date and that yet to come. There
will be a display of plans and photographs. Please make a
special effort to come.
...
Prayer for St Stephen's Project
... Benedicite |

Burnt-out ridge is repaired
|
|
November
(Richard writes) … progress continues and, in recent weeks, the
north aisle parapet has been rebuilt, the east gable damage has
been completely repaired, ‘tile stitching’ on the tower is under
way, the stair tower brickwork has been redone, and the roof
structure ‘felted’ and re-battened - and is now water-proof
(hooray!).
The completion date is now set for Feb 29th - does anyone have
any ideas for a publicity stunt (preferably legal, decent and
non-fattening) to mark it?
**and don’t forget the one-woman show on Saturday 3rd
November by Gabrielle Drake entitled Dear Scheherezade – Mrs
Gaskell in her own words. 7.30pm in the New Theatre, Friars
Walk. Proceeds to the project.
|
 |
|
4th October
We understand that the roof structure is proving
to be in slightly better repair than expected, but the East
gable is in a worse state! The builders are currently estimating
March 13th 2008 as the completion date for the various Phase 1
repairs. Plans are now well in hand for moving the organ
in St Stephen’s into St Mary Arches.
As part of the programme of Autumn events, there
will be a one-woman show on 3rd November by Gabrielle Drake
entitled Dear Scheherezade – Mrs Gaskell in her own words. Watch
for notices! |
 |
|
September 4th During August there
was considerable media interest in St Stephen’s church following
the exposure of blitz damage to the roof timbers and speculation
concerning the inspection of the 11th century crypt. Evidence of
the slow incendiary bomb burning in the central timbers
supporting the roof was revealed once all the slates had been
removed. Photographs show that St Stephens is the only building
to remain standing in this part of Exeter following the
devastating blitz of May 1942. The slow burn probably lasted for
months or even years and was kept in check by the hardness of
the ancient oak beams and the relative lack of oxygen in the
roof space. A second TV documentary company has expressed
interest in the crypt. |
 |
|
August 2007
The
church is now enclosed in protective sheeting and work has
commenced on the roof. The inside of the building has been
stripped of valuable items (tapestry, Charles 1st coat of arms,
pictures etc.) and the organ has been encased with protective
material. The tapestry is being cleaned and stored during its
absence. All this in case the ceiling does not hold out!
Twelve posters – prepared by a graphic artist – have been
placed on the hoarding around the church. Thanks to those who
have worked at this and who have met the necessary cost.
A visit has been made to Chagford Church where the church
interior has been re-built following designs by the architect
preparing our own changes. All were very impressed. By the end
of 2010, St Stephen’s will be looking very different.
Discussions continue with two major funding agencies
concerning the second phase of the project while arrangements
continue for the proposed moving of the organ to St Mary Arches
and an assessment of the crypt (which has not been officially
opened since 1826).
The Events Committee have decided there should be no
lunch-time concerts during August this year. For safety reasons
we have agreed that St Stephen’s will remain closed during the
week.
The first progress report from the builders indicates there
have been no accidents and that the security staff have been
called out twice concerning trespass onto the scaffolding. No
intruders were found.
See
Report of activities in July & August for more details. |
 |
|
Exeter's Express & Echo
features the St Stephen's Project (26th July)
TRUE EXTENT OF BLITZ DAMAGE TO CHURCH IS REVEALED BY BUILDERS
They are raising the roof at one of Exeter's
oldest and most-loved churches - and giving thanks it's still
there.
For a study of the now-exposed ancient beams
shows that it could have been on fire for years.
St Stephen's, which has stood in the High
Street since Saxon times, is undergoing a major £1m restoration.
And now that the slates are off, the damage
that was caused by an incendiary bomb during the Blitz in 1942
can be fully appreciated....
from
www.thisisexeter.co.uk, website of the Express & Echo
|

 |
|
29th June
The scaffolders arrived – unannounced – at the beginning of
June. While this was three weeks early it was welcomed as a sign
that, at last, the Project had really started. During the whole
of June the work continued and the church is now enveloped in
scaffolding and sheeting and surrounded by grey-painted
hoarding. A major development has been the commissioning of an
artist/graphic designer to provide posters on the hoarding
describing St Stephen’s and the Project. This commission, which
resulted from a donation from a Parish member, will be displayed
in July
See
Report of activities in
May & June for more details.
|

The restoration continues under cover |
|
26th May
The contracts have been signed and meetings have taken place
with the builders - Ellis and Co. The plan is for closure
to start from Monday 21st May, with scaffolding and boarding
being erected around the church during that week. But watch out
for notices about this, as much depends on how quickly the
builder receives a permit to erect the scaffolding on the public
highway |

Scaffolding rises - 3rd June |
|
25th March
We have raised the money needed to start the first phase of the
project – the essential repairs to the roof and tower will begin
shortly. A big thank you to everyone who has made this possible.
We now move on to the next phase: the improvements to the inside
of the church. We still have a long way to go but with your help
we will get there!
See
Report of activities in March & April for more details. |
|
|
End February
This is a time of waiting …… and waiting. Before being able to
proceed with the repairs to the roof and tower it is necessary
for us to obtain permission to proceed from both the Diocese and
from English Heritage. The Diocese has responsibility for
ensuring that what is done to the building is both appropriate
and to be undertaken efficiently; English Heritage provides
about half the cost of the necessary repairs and will only
release their grant if they are satisfied that our heritage is
being appropriately cared for and that what we propose for the
roof and tower is architecturally necessary and efficiently
planned.
See
Report of activities in Jan & Feb for more details. |

Damage inside the church |