Need to repair roof and refurbish interior of St Stephen's
recognised.
Consultations undertaken with various local and national
bodies and with users of the building.
2004
Architect's plans for roof and tower and
conceptual drawings for interior widely shared. Second set accepted after three rounds of
local and national
consultations.
Archaeological, access, cost survey reports commissioned and
received.
Project display inside St Stephen's Church
Public displays of proposed changes with invitation to
comment
Application (failed) to English Heritage for Phase 1 (roof/
tower) funding support.
High Street banner
2005
Patrons (Lord Mayor/Bishop/MP) accept
invitation.
Risk analysis undertaken.
Application (roof/tower repair) to English Heritage
re-submitted (successful).
2006
Vehicular access to building agreed.
Public fundraising launch; Phase 1 matched
funding raised.
Design team established; website set up.
Permissions to proceed with Phase 1 works
obtained.
2007/8
Phase 1 works undertaken - scaffold, hoarding,
sheeted elevations and roof coverings. Removal and
reinstatement of slated and lead roof to building, tower and
spire.
Roof found to be seriously 'blitz' damaged,
tower required strengthening and parapet over the High
Street pavement was in a dangerous condition.
Roof and tower repairs completed in 2008
2009
'Access for all' policy agreed after
wide consultation (inc. focus groups).
Preliminary archaeological assessment of
crypt undertaken.
Removal, restoration and relocation of
historic pipe organ undertaken.
Staged progression of Phases 2 to 5 discussed and
budget estimate agreed.
Successful grant application to Viridor
Credits
Environment Co. (Landfill Community Fund) submitted.
Collecting box displayed daily in High Street
2010
Planning and ecclesiastical permissions to
proceed with Phases 2 - 5 obtained.
Asbestos, monument care, heating and
lighting surveys commissioned.
Re-structuring of management team
undertaken.
Funds to meet estimated cost of Phase 2 and
part of Phase 3 obtained.
Tender for Phase 2 works with start date in
January 2011 accepted.
Fundraising continues and reaches a total of
£1 million by the year-end.
2011 (to August)
Phase 2 (internal & external walls) works
commenced in January and completed in May.
Additional grant from Viridor Credits makes
it possible to commence Phase 3.
Phase 3 (internal refurbishment) commenced
in June.
Removal of contents including Kitchen,
Vestry, Tower Room, Porch, Dias, Floor completed.
Preparation for internal ramp completed.
New stone floor prepared.
West End large window revealed.
Fund-raising reaches £1.35M - 88% of total
sum needed.